Chemistry Explain daily providing Q&A content “#93 A proposed embankment fill requires 3500 m3 of compacted soil” in Civil Engineering, Civil engineering career, Civil engineering companies near me, Civil engineering firms near me.Get the Free Online Chemistry Q&A Questions And Answers with explain. To crack any examinations and Interview tests these Chemistry Questions And Answers are very useful. Here we have uploaded the Free Online Chemistry Questions. Here we are also given the all chemistry topic.
Chemistry Explain team has covered all Topics related to inorganic, organic, physical chemistry, and others So, Prepare these Chemistry Questions and Answers with Explanation Pdf.
For More Chegg Questions
Free Chegg Question
A proposed embankment fill requires 3500 m3 of compacted soil. The void ratio of the compacted fill is specified as 0.65. Four borrow pits are available, as described in the following table, which lists the respective void ratios of the soil and the cost per cubic meter for moving the soil to the proposed construction site. Make the necessary calculations to select the pit from which the soil should be bought to minimize the cost. Assume Gs to be the same at all pits.Borrow pit | Void ratio | Cost ($/m3) |
A | 0.85 | 9 |
B | 1.2 | 6 |
C | 0.95 | 7 |
D | 0.75 | 10 |
Free Chegg Answer
Find the dry unit weight using the formula.
â¦â¦ (1)
Here, is specific gravity of soil solids, is unit weight of water, and e is void ratio.
Substitute for and 0.65 for e.
â¦â¦ (2)
Find the dry unit weight soil required for compacted soil using Equation (2).
Thus, the volume of soil to be excavated from borrow pit is .
Find the dry unit weight of soil for borrow pit A using Equation (1).
Substitute for and 0.85 for e.
Similarly, calculate for borrow pit B, C, and D and tabulate the values in Table (1).
â¦â¦ (1)
Here, is specific gravity of soil solids, is unit weight of water, and e is void ratio.
Substitute for and 0.65 for e.
â¦â¦ (2)
Find the dry unit weight soil required for compacted soil using Equation (2).
Thus, the volume of soil to be excavated from borrow pit is .
Find the dry unit weight of soil for borrow pit A using Equation (1).
Substitute for and 0.85 for e.
Similarly, calculate for borrow pit B, C, and D and tabulate the values in Table (1).
Find the volume to be excavated (V) from the borrow pit A using the calculation.
Substitute for .
Similarly, calculate for borrow pit B, C, and D and tabulate the values in Table (1).
Find the total cost for borrow pit A using the formula.
Substitute for V and 9$ for cost.
Similarly, calculate for borrow pit B, C, and D and tabulate the values in Table (1).
Substitute for .
Similarly, calculate for borrow pit B, C, and D and tabulate the values in Table (1).
Find the total cost for borrow pit A using the formula.
Substitute for V and 9$ for cost.
Similarly, calculate for borrow pit B, C, and D and tabulate the values in Table (1).
Tabulate dry unit weight, volume, and total cost for borrow pit A, B, C, and D as in Table (1).
Thus, the soil should be bought to minimize the cost.
Borrow pit | Void ratio (e) | at borrow pit | Cost | Total cost ($) | |
A | 0.85 | 3926.2 | 9 | 35,335.8 $ | |
B | 1.2 | 4665.7 | 6 | 27,994.2 $ | |
C | 0.95 | 4128.8 | 7 | 28,959 $ | |
D | 0.75 | 3709.3 | 10 | 37,093 $ |